Second, the boot before the operations, the following conditions should be recognized in a safe state before boot:
(1) All controllers are set to zero position;
(2) Cranes and operationally independent of whether the district personnel, operations personnel are evacuated to a safe area;
(3) whether there is within the operating range of the crane is not cleared of obstructions;
(4) Cranes and other equipment or fixed minimum distance is in a building more than 0.5m;
(5) Supply disconnecting device is locked or there are warning signs;
(6) whether the requirements of mobile cranes smooth good venue, securely and reliably lay legs.
Third, before driving, must-ringing or alert; operations close to people, it should give intermittent tone or warning.
Fourth, the driver during normal operation, shall not carry out the following acts:
(A) the use of privilege position limiter parking;
(2) the use of anti-vehicle hit the brake;
(3) lifting operations during inspection and maintenance;
(4) adjustment with load hoisting, luffing mechanism of the brakes, or the load increases operating range;
(5) shall not hanging from the top of the head through, hanging objects and the boom shall not stand on.
Fifth, in strict accordance with the command signal operation of the emergency stop signal, whoever issued, must be implemented immediately.
Sixth, hanging out near or rating, or lifting of dangerous goods (liquid metal, hazardous materials, flammable and explosive materials), the brake check carefully before lifting, and with a small height, try hanging a short trip, make sure there is no problem after then lifting.
Seventh, the various parts of the crane, hanging out with power lines and auxiliary equipment shall meet the minimum safety distance requirements;
Eighth, with the following conditions, the driver should not be operated:
(1) crane structure or component (such as a hook, wire rope, brake, safety devices, etc.) affect the safety defects and damage;
(2) hanging objects may be overloaded or overloaded, the weight lifting is unclear, embedded or frozen in the ground, squeezed by other objects, in operation shall not be pulled oblique hanging crooked;
(3) hanging objects bundling is not strong, or hanging swings, weight between angular and not padded sling; hanging objects floating on someone or compartment;
(4) jobsites dim, blind venue, hanging objects situations or command signals.
Ninth, work in a power outage, should all controllers set to zero, turn off the power. Back to work, you should first check the crane is working properly, that it is safe before normal operation.
Tenth, there are primary and secondary sets of hoisting mechanism, does not allow the use of both primary and secondary hook work (special design allows the crane to go out).
Eleventh, with the same two or more cranes lifting heavy loads, each crane are not overloaded. Transporting process should remain vertical rope, keep running simultaneously. When lifting, the responsible technical personnel and security personnel should be present technical guidance.
Twelfth, open operation track crane, when the wind is greater than 6, it should stop working; when the job is finished, should anchor horde cranes.